Updated as of
|
|
11/19/2024
|
|
|
|
|
Listed
below is a summary of the planned outages that could affect capacity or
impact any receipt/delivery locations during the Rover 2024 outage season.
This schedule is not a complete list of all outages and is subject to change
as the season progresses to reflect any project delays, cancellations or
additions. Additionally, anticipated impact and restrictions are subject to
change.
*All scheduled dates represent gas days as defined in the Rover Tariff to
mean a period of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
|
Start Date
|
End Date
|
Location
|
Unit(s)
|
Maintenance
|
Anticipated Impact
|
Meter(s) Impact
|
1/3/24
|
1/3/24
|
Wayne
|
201
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
1/4/24
|
1/4/24
|
Wayne
|
202
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
1/8/24
|
1/9/24
|
Leesville
|
201
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
1/9/24
|
1/9/24
|
Majorsville
|
201
|
Preventative Maintenance
|
Capacity through
Majorsville station limited. Meter subject to scheduling reductions.
|
70004
|
1/9/24
|
1/9/24
|
Crawford
|
203
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
1/10/24
|
1/10/24
|
Wayne
|
203
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
1/11/24
|
1/11/24
|
Crawford
|
202
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
1/15/24
|
2/9/24
|
Leesville
|
202
|
Major Overhaul
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
1/16/24
|
1/16/24
|
Crawford
|
201
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
1/18/24
|
1/18/24
|
Majorsville
|
203
|
Preventative Maintenance
|
Capacity through
Majorsville station limited. Meter subject to scheduling reductions.
|
70004
|
1/23/24
|
1/24/24
|
Crawford
|
205
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
1/24/24
|
1/24/24
|
Sherwood
|
202
|
Preventative Maintenance
|
Capacity through Sherwood
station limited. Meter subject to scheduling reductions.
|
70001
|
1/25/24
|
1/25/24
|
Crawford
|
204
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
1/29/24
|
1/29/24
|
Majorsville
|
202
|
Preventative Maintenance
|
Capacity through
Majorsville station limited. Meter subject to scheduling reductions.
|
70004
|
2/7/24
|
2/7/24
|
Sherwood
|
203
|
Preventative Maintenance
|
Capacity through Sherwood
station limited. Meter subject to scheduling reductions.
|
70001
|
2/7/24
|
2/7/24
|
Crawford
|
201
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
2/19/24
|
3/19/24
|
Wayne
|
203
|
Major Overhaul
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
3/13/24
|
3/13/24
|
Sherwood
|
201
|
Preventative Maintenance
|
Capacity through Sherwood
station limited. Meter subject to scheduling reductions.
|
70001
|
3/13/24
|
3/13/24
|
Sherwood
|
203
|
Preventative Maintenance
|
Capacity through Sherwood
station limited. Meter subject to scheduling reductions.
|
70001
|
3/25/24
|
4/19/24
|
Leesville
|
201
|
Major Overhaul
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
3/25/24
|
4/1/24
|
Wayne
|
204
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
4/2/24
|
4/5/24
|
Wayne
|
205
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
4/2/24
|
4/2/24
|
Majorsville
|
201
|
Preventative Maintenance
|
Capacity through
Majorsville station limited. Meter subject to scheduling reductions.
|
70004
|
4/8/24
|
4/11/24
|
Crawford
|
203
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
4/15/24
|
4/18/24
|
Wayne
|
206
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
4/17/24
|
4/17/24
|
Majorsville
|
Whole Station
|
ESD
|
Capacity through
Majorsville Station Limited. Meter subject to scheduling reductions.
|
70004
|
4/23/24
|
4/26/24
|
Crawford
|
202
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
4/22/24
|
4/23/24
|
Wayne
|
multiple units
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
4/24/24
|
4/25/24
|
Leesville
|
Station
|
Main Breaker Upgrade &
ESD
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
4/24/24
|
4/24/24
|
Wick
|
Meter Station
|
OPP Valve Work
|
Capacity through Wick
Meter Station limited. Meter subject to scheduling reductions.
|
70045
|
4/29/24
|
5/24/24
|
Wayne
|
201
|
Major Overhaul
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
5/2/24
|
5/2/24
|
Majorsville
|
203
|
Preventative Maintenance
|
Capacity through
Majorsville station limited. Meter subject to scheduling reductions.
|
70004
|
5/6/24
|
5/10/24
|
Majorsville
|
201
|
Major Overhaul
|
Capacity through
Majorsville station limited. Meter subject to scheduling reductions.
|
70004
|
5/9/24
|
5/9/24
|
Sherwood
|
Whole Station
|
ESD
|
Capacity through Sherwood
Station limited. Meter subject to scheduling reductions.
|
70001
|
5/14/24
|
5/17/24
|
Sherwood
|
201
|
Preventative Maintenance
|
Capacity through Sherwood
station limited. Meter subject to scheduling reductions.
|
70001
|
5/17/24
|
5/17/24
|
Majorsville
|
multiple units
|
Preventative Maintenance
|
Capacity through
Majorsville station limited. Meter subject to scheduling reductions.
|
70004
|
5/21/24
|
5/21/24
|
Wayne
|
Station
|
ESD
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
5/28/24
|
5/31/24
|
Crawford
|
201
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
5/30/24
|
5/30/24
|
Majorsville
|
202
|
Preventative Maintenance
|
Capacity through
Majorsville station limited. Meter subject to scheduling reductions.
|
70004
|
6/2/24
|
6/10/24
|
Wayne
|
202
|
Major Overhaul
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
6/4/24
|
6/7/24
|
Sherwood
|
202
|
Preventative Maintenance
|
Capacity through Sherwood
station limited. Meter subject to scheduling reductions.
|
70001
|
6/12/24
|
6/13/24
|
Leesville
|
206
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
6/25/24
|
6/28/24
|
Sherwood
|
203
|
Preventative Maintenance
|
Capacity through Sherwood
station limited. Meter subject to scheduling reductions.
|
70001
|
7/16/24
|
7/16/24
|
Majorsville
|
multiple units
|
Install oil platforms
|
Capacity through
Majorsville station limited. Meter subject to scheduling reductions.
|
70004
|
7/24/24
|
7/24/24
|
Bulger
|
Whole Station
|
ESD
|
Pressure Fluctuations
|
70005
|
8/14/24
|
8/14/24
|
Seneca
|
Whole Station
|
ESD
|
Capacity through Seneca
Station Limited. Meters subject to scheduling reductions.
|
70002, 70016, 70012
|
8/15/24
|
8/16/24
|
Crawford
|
204
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
8/19/24
|
8/20/24
|
Leesville
|
202
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
8/20/24
|
8/20/24
|
Bulger
|
201
|
Preventative Maintenance
|
Capacity through Bulger
station limited. Meter subject to scheduling reductions.
|
70005
|
8/21/24
|
8/21/24
|
Clarington
|
Whole Station
|
ESD
|
Capacity through
Clarington Station limited. Meter subject to scheduling reductions.
|
70011
|
8/21/24
|
8/21/24
|
Crawford
|
Station
|
ESD
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
8/23/24
|
8/23/24
|
Bulger
|
202
|
Preventative Maintenance
|
Capacity through Bulger
station limited. Meter subject to scheduling reductions.
|
70005
|
8/27/24
|
8/28/24
|
Leesville
|
204
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
9/2/24
|
9/6/24
|
Crawford
|
205
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
9/11/24
|
9/11/24
|
Sherwood
|
201
|
Preventative Maintenance
|
Capacity through Sherwood
station limited. Meter subject to scheduling reductions.
|
70001
|
9/23/24
|
9/27/24
|
Majorsville
|
203
|
Major Overhaul
|
Capacity through
Majorsville station limited. Meter subject to scheduling reductions.
|
70004
|
9/25/24
|
9/25/24
|
Cadiz
|
Whole Station
|
ESD
|
Capacity through Cadiz
Station limited. Meters subject to scheduling reductions.
|
70017, 70003
|
10/3/24
|
10/3/24
|
Sherwood
|
202
|
Preventative Maintenance
|
Capacity through Sherwood
station limited. Meter subject to scheduling reductions.
|
70001
|
10/8/24
|
10/8/24
|
Crawford
|
203
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
10/9/24
|
10/9/24
|
Wayne
|
203
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
10/10/24
|
10/10/24
|
Crawford
|
202
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
10/14/24
|
10/18/24
|
Majorsville
|
202
|
Major Overhaul
|
Capacity through
Majorsville station limited. Meter subject to scheduling reductions.
|
70004
|
10/14/24
|
10/18/24
|
Leesville
|
205
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
10/21/24
|
10/25/24
|
Leesville
|
206
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
10/22/24
|
10/22/24
|
Majorsville
|
201
|
Preventative Maintenance
|
Capacity through
Majorsville station limited. Meter subject to scheduling reductions.
|
70004
|
10/23/24
|
10/23/24
|
Sherwood
|
203
|
Preventative Maintenance
|
Capacity through Sherwood
station limited. Meter subject to scheduling reductions.
|
70001
|
10/28/24
|
11/29/24
|
Bulger
|
201
|
Overhaul
|
Capacity through Bulger station limited. Meter subject
to scheduling reductions.
|
70005
|
11/5/24
|
11/5/24
|
Wayne
|
various units
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
11/6/24
|
11/6/24
|
Crawford
|
201
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
11/12/24
|
11/12/24
|
Wayne
|
201
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
12/10/24
|
12/10/24
|
Crawford
|
various units
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline capacity
limited
|
1/6/25
|
1/31/25
|
Wayne
|
202
|
Overhaul
|
Mainline capacity may be limited; IT and Secondary Out of
Path nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
2/10/25
|
3/7/25
|
Crawford
|
201
|
Overhaul
|
Mainline capacity may be limited; IT and Secondary Out of
Path nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
3/17/25
|
4/11/25
|
Crawford
|
202
|
Overhaul
|
Mainline capacity may be limited; IT and Secondary Out of
Path nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
4/21/25
|
5/16/25
|
Crawford
|
203
|
Overhaul
|
Mainline capacity may be limited; IT and Secondary Out of
Path nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|