Updated
as of
|
|
1/13/2025
|
|
|
|
|
Listed
below is a summary of the planned outages that could affect capacity or
impact any receipt/delivery locations during the Rover 2024 outage season.
This schedule is not a complete list of all outages and is subject to change
as the season progresses to reflect any project delays, cancellations or
additions. Additionally, anticipated impact and restrictions are subject to
change.
*All scheduled dates represent gas days as defined in the Rover Tariff to
mean a period of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
|
Start Date
|
End Date
|
Location
|
Unit(s)
|
Maintenance
|
Anticipated Impact
|
Meter(s) Impact
|
1/3/24
|
1/3/24
|
Wayne
|
201
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
1/4/24
|
1/4/24
|
Wayne
|
202
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
1/8/24
|
1/9/24
|
Leesville
|
201
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
1/9/24
|
1/9/24
|
Majorsville
|
201
|
Preventative Maintenance
|
Capacity through Majorsville station limited. Meter subject to
scheduling reductions.
|
70004
|
1/9/24
|
1/9/24
|
Crawford
|
203
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
1/10/24
|
1/10/24
|
Wayne
|
203
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
1/11/24
|
1/11/24
|
Crawford
|
202
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
1/15/24
|
2/9/24
|
Leesville
|
202
|
Major Overhaul
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
1/16/24
|
1/16/24
|
Crawford
|
201
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
1/18/24
|
1/18/24
|
Majorsville
|
203
|
Preventative Maintenance
|
Capacity through Majorsville station limited. Meter subject to
scheduling reductions.
|
70004
|
1/23/24
|
1/24/24
|
Crawford
|
205
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
1/24/24
|
1/24/24
|
Sherwood
|
202
|
Preventative Maintenance
|
Capacity through Sherwood station limited. Meter subject to
scheduling reductions.
|
70001
|
1/25/24
|
1/25/24
|
Crawford
|
204
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
1/29/24
|
1/29/24
|
Majorsville
|
202
|
Preventative Maintenance
|
Capacity through Majorsville station limited. Meter subject to
scheduling reductions.
|
70004
|
2/7/24
|
2/7/24
|
Sherwood
|
203
|
Preventative Maintenance
|
Capacity through Sherwood station limited. Meter subject to
scheduling reductions.
|
70001
|
2/7/24
|
2/7/24
|
Crawford
|
201
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
2/19/24
|
3/19/24
|
Wayne
|
203
|
Major Overhaul
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
3/13/24
|
3/13/24
|
Sherwood
|
201
|
Preventative Maintenance
|
Capacity through Sherwood station limited. Meter subject to
scheduling reductions.
|
70001
|
3/13/24
|
3/13/24
|
Sherwood
|
203
|
Preventative Maintenance
|
Capacity through Sherwood station limited. Meter subject to
scheduling reductions.
|
70001
|
3/25/24
|
4/19/24
|
Leesville
|
201
|
Major Overhaul
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
3/25/24
|
4/1/24
|
Wayne
|
204
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
4/2/24
|
4/5/24
|
Wayne
|
205
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
4/2/24
|
4/2/24
|
Majorsville
|
201
|
Preventative Maintenance
|
Capacity through Majorsville station limited. Meter subject to
scheduling reductions.
|
70004
|
4/8/24
|
4/11/24
|
Crawford
|
203
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
4/15/24
|
4/18/24
|
Wayne
|
206
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
4/17/24
|
4/17/24
|
Majorsville
|
Whole Station
|
ESD
|
Capacity through Majorsville Station Limited. Meter subject to
scheduling reductions.
|
70004
|
4/23/24
|
4/26/24
|
Crawford
|
202
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
4/22/24
|
4/23/24
|
Wayne
|
multiple units
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
4/24/24
|
4/25/24
|
Leesville
|
Station
|
Main Breaker Upgrade & ESD
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
4/24/24
|
4/24/24
|
Wick
|
Meter Station
|
OPP Valve Work
|
Capacity through Wick Meter Station limited. Meter subject to
scheduling reductions.
|
70045
|
4/29/24
|
5/24/24
|
Wayne
|
201
|
Major Overhaul
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
5/2/24
|
5/2/24
|
Majorsville
|
203
|
Preventative Maintenance
|
Capacity through Majorsville station limited. Meter subject to
scheduling reductions.
|
70004
|
5/6/24
|
5/10/24
|
Majorsville
|
201
|
Major Overhaul
|
Capacity through Majorsville station limited. Meter subject to
scheduling reductions.
|
70004
|
5/9/24
|
5/9/24
|
Sherwood
|
Whole Station
|
ESD
|
Capacity through Sherwood Station limited. Meter subject to
scheduling reductions.
|
70001
|
5/14/24
|
5/17/24
|
Sherwood
|
201
|
Preventative Maintenance
|
Capacity through Sherwood station limited. Meter subject to
scheduling reductions.
|
70001
|
5/17/24
|
5/17/24
|
Majorsville
|
multiple units
|
Preventative Maintenance
|
Capacity through Majorsville station limited. Meter subject to
scheduling reductions.
|
70004
|
5/21/24
|
5/21/24
|
Wayne
|
Station
|
ESD
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
5/28/24
|
5/31/24
|
Crawford
|
201
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
5/30/24
|
5/30/24
|
Majorsville
|
202
|
Preventative Maintenance
|
Capacity through Majorsville station limited. Meter subject to
scheduling reductions.
|
70004
|
6/2/24
|
6/10/24
|
Wayne
|
202
|
Major Overhaul
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
6/4/24
|
6/7/24
|
Sherwood
|
202
|
Preventative Maintenance
|
Capacity through Sherwood station limited. Meter subject to
scheduling reductions.
|
70001
|
6/12/24
|
6/13/24
|
Leesville
|
206
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
6/25/24
|
6/28/24
|
Sherwood
|
203
|
Preventative Maintenance
|
Capacity through Sherwood station limited. Meter subject to
scheduling reductions.
|
70001
|
7/16/24
|
7/16/24
|
Majorsville
|
multiple units
|
Install oil platforms
|
Capacity through Majorsville station limited. Meter subject to
scheduling reductions.
|
70004
|
7/24/24
|
7/24/24
|
Bulger
|
Whole Station
|
ESD
|
Pressure Fluctuations
|
70005
|
8/14/24
|
8/14/24
|
Seneca
|
Whole Station
|
ESD
|
Capacity through Seneca Station Limited. Meters subject to
scheduling reductions.
|
70002, 70016, 70012
|
8/15/24
|
8/16/24
|
Crawford
|
204
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
8/19/24
|
8/20/24
|
Leesville
|
202
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
8/20/24
|
8/20/24
|
Bulger
|
201
|
Preventative Maintenance
|
Capacity through Bulger station limited. Meter subject to
scheduling reductions.
|
70005
|
8/21/24
|
8/21/24
|
Clarington
|
Whole Station
|
ESD
|
Capacity through Clarington Station limited. Meter subject to
scheduling reductions.
|
70011
|
8/21/24
|
8/21/24
|
Crawford
|
Station
|
ESD
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
8/23/24
|
8/23/24
|
Bulger
|
202
|
Preventative Maintenance
|
Capacity through Bulger station limited. Meter subject to
scheduling reductions.
|
70005
|
8/27/24
|
8/28/24
|
Leesville
|
204
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
9/2/24
|
9/6/24
|
Crawford
|
205
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
9/11/24
|
9/11/24
|
Sherwood
|
201
|
Preventative Maintenance
|
Capacity through Sherwood station limited. Meter subject to
scheduling reductions.
|
70001
|
9/23/24
|
9/27/24
|
Majorsville
|
203
|
Major Overhaul
|
Capacity through Majorsville station limited. Meter subject to
scheduling reductions.
|
70004
|
9/25/24
|
9/25/24
|
Cadiz
|
Whole Station
|
ESD
|
Capacity through Cadiz Station limited. Meters subject to
scheduling reductions.
|
70017, 70003
|
10/3/24
|
10/3/24
|
Sherwood
|
202
|
Preventative Maintenance
|
Capacity through Sherwood station limited. Meter subject to
scheduling reductions.
|
70001
|
10/8/24
|
10/8/24
|
Crawford
|
203
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
10/9/24
|
10/9/24
|
Wayne
|
203
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
10/10/24
|
10/10/24
|
Crawford
|
202
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
10/14/24
|
10/18/24
|
Majorsville
|
202
|
Major Overhaul
|
Capacity through Majorsville station limited. Meter subject to
scheduling reductions.
|
70004
|
10/14/24
|
10/18/24
|
Leesville
|
205
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
10/21/24
|
10/25/24
|
Leesville
|
206
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
10/22/24
|
10/22/24
|
Majorsville
|
201
|
Preventative Maintenance
|
Capacity through Majorsville station limited. Meter subject to
scheduling reductions.
|
70004
|
10/23/24
|
10/23/24
|
Sherwood
|
203
|
Preventative Maintenance
|
Capacity through Sherwood station limited. Meter subject to
scheduling reductions.
|
70001
|
10/28/24
|
12/13/24
|
Bulger
|
201
|
Overhaul
|
Capacity through Bulger station limited. Meter subject to
scheduling reductions.
|
70005
|
11/5/24
|
11/5/24
|
Wayne
|
various units
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
11/6/24
|
11/6/24
|
Crawford
|
201
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
11/12/24
|
11/12/24
|
Wayne
|
201
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
12/9/24
|
12/9/24
|
Sherwood
|
201
|
Preventative Maintenance
|
Capacity through Sherwood station limited. Meter subject to
scheduling reductions.
|
70001
|
12/10/24
|
12/11/24
|
Bulger
|
Station
|
Emissions Testing
|
Capacity through Bulger station limited. Meter subject to
scheduling reductions.
|
70005
|
12/11/24
|
12/11/24
|
Crawford
|
various units
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
12/17/24
|
12/17/24
|
Crawford
|
various units
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of Path
nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|