| Notice Type Description: | Planned Service Outage |
| Notice Identifier: | 115188 |
| Critical Notice Description: | Critical notice |
| Posting Date/Time: | Feb 16 2026 2:23PM |
| Notice Status Description: | Initiate |
| Required Response Indicator Description: | No response required |
| Response Date/Time: | |
| TSP: | 7933047 |
| TSP Name: | TRANSWESTERN PIPELINE COMPANY, LLC |
| Subject: | La Plata Compressor Station - ESD/Safety device testing & annual maintenance. 6/2 thru 6/4/26 |
| Notice Effective Date/Time: | Jun 2 2026 9:00AM |
| Notice End Date/Time: | Jun 5 2026 8:59AM |
|
Notice Text: Nominated Volume Affected |
February 16, 2026 To: All Transwestern Pipeline Customers Subject: La Plata Compressor Station Annual Maintenance Reason: Transwestern will be performing ESD/Safety device testing & annual maintenance at the La Plata Compressor Station located on the San Juan Lateral. Gas Day June 2nd thru June 4th, 2026 (3 days) La Plata Compressor Station Capacity will be reduced from 500,000 MMBtu/d to 0 MMBtu/d. Gas Day June 5th, 2026 La Plata Compressor Station Capacity will increase from 0MMBtu/d to 500,000MMBtu/d. La Plata Interconnects affected: POI 500536 - BP Florida - Zero flow all three days. POI 500535 - Harvest/Ignacio - Zero flow all three days. POI 500533 - Northwest/Ignacio - Zero flow all three days. Transwestern reserves the right to revise the above listed schedule. Please continue to monitor the Transwestern website for updates and schedule changes. |
| Reason: | Pipeline Maintenance |
| Location: | La Plata Compressor Station - Located on the Ignacio to Blanco Lateral |