| Notice Type Description: | Planned Service Outage |
| Notice Identifier: | 115189 |
| Critical Notice Description: | Critical notice |
| Posting Date/Time: | Feb 16 2026 2:40PM |
| Notice Status Description: | Initiate |
| Required Response Indicator Description: | No response required |
| Response Date/Time: | |
| TSP: | 7933047 |
| TSP Name: | TRANSWESTERN PIPELINE COMPANY, LLC |
| Subject: | Bloomfield Compressor Station - ESD/Safety device testing & annual maintenance. 5/5 thru 5/9/26 |
| Notice Effective Date/Time: | May 5 2026 9:00AM |
| Notice End Date/Time: | May 10 2026 8:59AM |
|
Notice Text: Nominated Volume Affected |
February 16, 2026 To: All Transwestern Pipeline Customers Subject: Bloomfield Compressor Station - Located on the San Juan Lateral. Reason: ESD/Safety device testing. Annual maintenance on Units 1 thru 5. Relief & OPP valve testing. Sub-station maintenance. Gas Day May 5th thru May 9th, 2026 (5 days) Bloomfield Capacity will be reduced from 1,610,000 MMBtu/dto 1,100,000 MMBtu/d. Based on current scheduled volumes through the Bloomfield Station (Blanco Hub), this maintenance may not impact any scheduled volumes during this timeframe. With the exception of Harvest Valverde, please see note below. Gas Day May 10th, 2026 Bloomfield Capacity will increase from 1,100,000 MMBtu/d to its original capacity of 1,610,000 MMBtu/d. Interconnects potentially affected: POI 56423 - Harvest Valverde (Zero flow for all 5 days - 5/5 thru 5/9). POI 500632-Trans-Colorado POI 56419 - Harvest Milagro POI 500516 - Harvest Kutz POI 78424 - Conoco Blanco Plant POI 500535 - Harvest Ignacio POI 500536 - IKAV (BP) Florida POI 500538 - Red Cedar Arkansas Loop POI 500533 &500534 - Northwest Ignacio POI 500631 - CEP La Plata |
| Reason: | Pipeline Maintenance |
| Location: | Bloomfield Compressor Station - Located on the San Juan Lateral. |