SPW
|
|
8/25/2026
|
8/28/2026
|
Panola Compressor Fall Maintenance Unit 2 and 3
|
Panola Compressor
|
Annual Maintenance
|
8
|
66227
|
|
9/1/2026
|
9/3/2026
|
Panola Compressor Fall Maintenance Unit 1
|
Panola Compressor
|
Annual Maintenance
|
8
|
66228
|
|
9/15/2026
|
9/21/2026
|
Markwest RTU
Installation
|
Markwest East
TX GR (#220050)
|
Meter Maintenance
|
8
|
67484
|
|
9/15/2026
|
9/22/2026
|
Vernon Compressor Fall Maintenance
|
Vernon Compressor
|
Annual Maintenance
|
8
|
66778
|
|
9/22/2026
|
9/25/2026
|
Eastrans DCP
Carthage RTU Installation
|
Eastrans DCP Carthage (#220015)
|
Meter Maintenance
|
8
|
67602
|
|
9/29/2026
|
10/1/2026
|
Alto Compressor Fall Maintenance
|
Alto Compressor
|
Annual Maintenance
|
8
|
67603
|
|
10/5/2026
|
10/9/2026
|
Westdale Compressor Fall Maintenance
|
Westdale Compressor
|
Annual Maintenance
|
8
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1. No capacity
impact is expected at this time.
|
|
2. Coordinating with
necessary loads.
|
|
3. Based on
historical and current throughput, no capacity impact is expected. In the event
nominations increase significantly, restrictions may become necessary.
|
|
4. Coordinating
maintenance with interconnecting pipe to minimize
customer impact. No capacity impact is
expected at this time; however, if operating conditions change, affected
parties will be notified.
|
|
5. Affected
production notified of shut-in during work.
|
|
6. Customers may experience
pressure fluctuations, but no capacity impact is anticipated.
|
|
7. Based upon
customer nominations, restrictions may become necessary.
|
|
8. Based on all
available information, capacity will be impacted. Capacity reductions will be done in accordance with the provisions of GR's tariff
regarding scheduling and interruption of services.
|